Custom process equipment, engineered before it’s built.

Pressure vessels, reactors, columns, separators and rotary equipment in carbon steel, stainless, duplex and nickel alloys. Every job starts with an engineer reading your drawing [confirm: every order].

ASME U · Certificate no. 42263 · National Board registered

Line drawing of a horizontal pressure vessel: inlet N1, outlet N2, drain N3, 2:1 semi-elliptical heads, two saddles, tangent-to-tangent length marked.

Fig. 1 — Horizontal pressure vessel, ASME VIII-1 · illustrative

What we build

We build four kinds of equipment, all engineered by the same team.

Every capability below is designed, calculated and built in the same Montréal shop, with the drawing checked before the steel is cut.

Line drawing of a vertical reactor: nozzle N1 on top, tangent-to-tangent height marked, skirt and legs.

ASME VIII-1 · U stamp

Pressure vessels & reactors

Code-stamped vessels and reactors, from first-of-a-kind reactors to repeat OEM vessels.

Plate

Up to 4 in [confirm]

Clad

SS316L

Pressure

1,200 psi (Enerkem)

Explore pressure vessels & reactors

Fig. 2 — Vertical reactor · illustrative

Line drawing of a horizontal separator with a mist pad beside a trayed vertical column on a skirt.

Separation

Separators & columns

Gas, RNG and oil-and-gas separators, adsorption vessels and self-supporting columns.

Service

Gas · RNG · oil & gas

Columns

Self-supporting

Internals

Trays, mist pads [confirm]

Explore separators & columns

Fig. 3 — Trayed column and separator · illustrative

Line drawing of a suction can and pump column over 30 ft long, held plumb, with a suction bell at the bottom.

Water & wastewater

Water pumping columns

Suction cans and pumping columns over 30 ft, held to tight vertical tolerance with sequenced welding.

Length

30 ft+

Alignment

Held in field (Sulzer)

Method

Weld sequencing

Explore water pumping columns

Fig. 4 — Suction can and pump column · illustrative

Line drawing of a sloped rotary kiln with riding rings and a girth gear.

Rotary & air separation

Rotary equipment & air separators

Rotary kilns, calciners, dryers and air separators for mineral and process plants.

Equipment

Kilns · calciners · dryers

Sector

Mining & aggregate

Scope

Fabrication [confirm]

Explore rotary equipment

Fig. 5 — Rotary kiln · illustrative

Engineering & design

The engineering comes first, so the fabrication goes right.

This is the path every drawing takes through Dimartech. Steps 02 and 03 are where design problems get caught, on paper, before they cost you in the shop or the field.

01

Your drawing or spec

P&ID, GA, datasheet or a problem

02

Design review

Code, materials, schedule, what we’d change

03

Calculations

ASME VIII-1, FEA, fatigue where needed

04

Fabrication drawings

Issued for your approval

05

Inspector acceptance

Calculations to your Authorized Inspector

06

Build, test, document

NDE, hydro, U-1A and the data book

Steps 02 and 03 make up the Pre-Fabrication Analysis. You see it before you commit [confirm terms].

Design review and redesign

When long-lead Inconel threatened a refinery shutdown, we redesigned the part with an overlay and met the date (AZZ).

Calculations and FEA

Fatigue analysis for vessels rated to 2,000,000 cycles, with 100% RT on every butt weld (Guild).

Design for manufacture

A prototype gasifier improved over three orders until it became a commercial product.

Spec sheet

Codes, materials and processes.

The short version of what your supplier file asks for. Items marked [confirm] are being verified with our quality team.

Codes & stamps

ASME Section VIII, Division 1 (U stamp), Certificate of Authorization no. 42263 · National Board registered · CRN [confirm provinces] · CSA B51 [confirm]

Materials

Carbon steel (e.g. SA-516-70) · stainless 304L / 316L · duplex · nickel alloys, including Inconel overlay

Welding & NDE

Qualified welders and procedures [confirm CWB W47.1] · RT, UT, MT and PT to your spec · PMI · hydrostatic test

Heat treatment & finishing

PWHT · machining · coatings · passivation, through a long-standing partner network

Shop

Pointe-aux-Trembles, Montréal · automated submerged-arc welding tower · turning rolls over 160 t · overhead cranes 30 t and 12 t [confirm] · maximum dimensions [confirm]

Documentation

U-1A data report · material test reports · NDE records · as-builts · bound, indexed data book

Certifications & quality

Qualify us in minutes.

Certificate numbers and issuing bodies, ready for your vendor file.

Verified

ASME U stamp

Certificate no. 42263 · Section VIII, Div. 1

Verified

National Board

Registered vessels (NB mark)

[confirm]

CRN

Canadian Registration Numbers by province

[confirm]

Quality system

CWB W47.1 · ISO 9001

Pre-Fabrication Analysis

Send a drawing. Get an engineer’s read on it.

What drives cost, what drives lead time, and what we’d change, with a firm bid or ROM estimate. Your drawings stay confidential.

Pre-Fabrication Analysis · sample layout

[Your project] · [Equipment] · Rev 0

01 · Cost drivers

Material grade, plate thickness, NDE scope

02 · Lead-time drivers

Long-lead forgings and alloys, inspector holds

03 · What we’d change

Design options that keep code and schedule

04 · Price

Firm bid or ROM estimate